What Determines the Price of a Shielded Room? 6 Factors to Know Before Getting a Quote
Two shielded rooms may look the same and still be priced very differently. We explain the main cost factors one by one.
Which values a shielded room specification for a tender or purchase must state, and the common mistakes to avoid, explained point by point.
For public institutions and large companies, buying a shielded room is often done through a tender or formal procurement process. In this process everything rests on the specification: companies bid according to the specification, bids are evaluated against it and delivery is accepted according to it. A vague or incomplete specification causes problems at every stage.
In this article we explain why a shielded room specification is so important, the technical values that must be included, common mistakes, acceptance and documentation requirements, and how maintenance and warranty should be defined. Our aim is to help you receive comparable bids and avoid disputes at handover.
Whether shielded room bids can be compared depends on how clear the specification is. Vague text leads companies to bid with different materials, different measurement methods and different door types. In the end the lowest price is often the most incomplete solution, and this shortfall only appears after installation, at the stage where it is hardest and most expensive to fix.
A good specification states clearly what the room will be used for, what performance it must deliver and how this performance will be proven. This way both the procurement team and the bidders are looking at the same target. At handover, the discussion then focuses only on whether the items written in the specification have been met.
The first section of the specification should describe what the room will be used for. Different uses such as EMC testing, digital forensics, confidential meetings, medical measurement or data processing require different performance targets and different equipment. When the intended use is written clearly, bidders can propose solutions that fit the need.
This section should also state how many people will work in the room, what equipment will be used, how long the room will be used each day and how often the door will be opened and closed. This information directly affects air conditioning, lighting and door selection. If the room may be expanded or moved in the future, this should also be in the specification.
The first item is the signal attenuation level: how many dB are required over which frequency range? A statement such as 'at least 100 dB between 10 kHz and 18 GHz' is much more useful than saying 'high performance'. If necessary, different values can be defined for different frequency bands. The measurement standard should be written alongside; EN 50147-1 or IEEE 299 is usually preferred.
Next come the internal dimensions, the number, type and clear opening of doors, the number and current ratings of power lines to be filtered, whether data lines will be fibre or copper, ventilation needs and interior fit-out. Because each of these values affects the bid price, every item left out makes the bids harder to compare. We explain measurement methods in our article how is shielding effectiveness measured.
The most common mistake is asking only for a dB value without stating the measurement method. If the measurement points and frequencies are not specified, everyone defends their own method at handover and the result becomes debatable. The second mistake is not defining the door separately; yet the door is where leakage is most often found, and the door type directly affects cost.
The third mistake is writing items that describe a particular brand or product. These items restrict competition and can be challenged in public tenders. Defining performance and function is the better approach. The fourth mistake is forgetting maintenance and warranty terms. Gaskets wear over time; if annual measurement and spare parts support are not required in the specification, the room may lose its original performance within a few years.
The specification should also include the conditions of the site where the room will be installed. The dimensions of the area, ceiling height, floor load capacity, the route for materials into the building and the existing electrical and air-conditioning infrastructure are needed for bidders to price accurately. Without this information, companies either add the risks to the price or ask for extra costs during installation.
If possible, bidders should be given the chance to visit the site during the tender. A site visit makes bids more realistic and helps reveal points that may have been missed in the specification. We have collected pre-installation preparation items as a checklist in our article on building preparation for a shielded room.
The specification should also list the documents to be delivered at handover: a signed measurement report, material certificates, as-built drawings, maintenance instructions and a training record. These documents will help both in audits and in future modifications. The calibration certificates of the measurement equipment should also be required as an attachment to the report.
Stating that the acceptance measurement will be made by an independent accredited body, and that the organisation's own technical team may attend, builds confidence. The corrections to be made and the conditions for re-measurement if a low value is found in the acceptance measurement should also be defined in advance. We explain how to prepare for acceptance in our article on preparing for the acceptance test.
Whether a shielded room keeps its performance over the years depends on regular maintenance. The specification should clearly define the warranty period, the components covered, the frequency of periodic measurement, spare parts delivery time and response time in the event of a fault. Spare parts support should be required especially for wearing parts such as door gaskets and filters.
Training for the staff who will use the room should also be part of the specification. The training should cover correct use of the door, protecting the gaskets, the rules to follow when bringing new equipment into the room and simple checks. In every project we support procurement teams by preparing a draft specification and compliance table as needed. For our measurement service, see our shielding measurement page.
It depends on the intended use. To reliably block phone and Wi-Fi signals, 80–100 dB is usually enough; TEMPEST and military applications require higher values and wider frequency ranges.
Yes. We prepare a free draft according to your needs; your organisation then adapts the final text to its own rules.
The acceptance measurement is made by an independent accredited body; the installing company coordinates the process. If you wish, your own team can also attend; this should be stated in the specification.
Usually not. Items describing a brand or product restrict competition. Defining performance and function is the better approach.
It depends on the project and organisational policy. Along with the warranty period, it is important to define scope, periodic measurement and spare parts support.
It is not mandatory but is recommended. A site visit makes bids more realistic and helps spot gaps in the specification early.
Related Solutions
Your free site survey and quote will be ready within 24 hours.
Two shielded rooms may look the same and still be priced very differently. We explain the main cost factors one by one.
The advantages of a container solution when you need a shielded space that can be moved to site without waiting for a building.
What electromagnetic compatibility testing is, which products are subject to it and what failing costs you.