EMC Lab Control Room Design: Why Separate and Shielded?

Why the control room next to an EMC test chamber, which houses the measurement equipment, should be shielded, and the design details.

When visiting an EMC laboratory, attention usually turns to the absorber-lined test chamber. But the place where measurements are managed, data collected and the product under test monitored is the control room right next to the test chamber. The design of the control room directly affects measurement accuracy, laboratory efficiency and staff comfort.

In this article we explain what the control room does, why it should be separate and shielded, how the penetrations between test chamber and control room are planned, the role of the amplifier room, product monitoring systems and working comfort.

What Does the Control Room Do?

The control room is the centre from which EMC tests are managed. Measurement receivers, spectrum analysers, signal generators, control computers and test software are located here. The test engineer controls the turntable and antenna mast from here, starts measurements and evaluates results. The operation of the product under test is also followed from here through cameras and monitoring systems.

Having measurement equipment and staff inside the test chamber adversely affects measurements. The equipment itself is a noise source and causes reflections; staff may be exposed to high fields in immunity tests. Having measurement equipment and staff outside the test chamber, in a separate control room, is therefore necessary for both measurement accuracy and safety.

Why Should It Be Shielded?

The computers, displays, measuring instruments and other electronic equipment in the control room generate electromagnetic noise themselves. This noise can reach the test chamber via cables going to it or through the walls and affect measurements. A shielded control room prevents this noise leaking into the test chamber.

High fields that may leak from the test chamber during immunity tests can also affect equipment and staff in the control room. A shielded control room prevents this too. The control room's shielding level does not have to be as high as the test chamber's; but it must ensure the noise generated by measurement equipment is suppressed to a level that does not affect measurements.

Penetrations and Cables

There are many connections between the test chamber and the control room: antenna cables, measurement cables, control signals, product monitoring connections and power lines. Each of these is a point that could compromise the shielding between the two rooms. Connections are therefore made through a specially designed penetration panel.

Shielded coaxial feedthroughs on the panel are used for RF measurement cables. Fibre optic links are preferred for control and monitoring signals; because fibre does not conduct electricity, it does not compromise shielding or carry noise. Power and other copper lines pass through filters. Including spare penetrations for future needs in the panel makes later changes easier. We explain cable shielding in detail in our article on cable shielding.

  • RF cables: shielded coaxial feedthroughs
  • Control and monitoring: fibre optic links
  • Power: power line filters
  • Spare penetrations: for future needs

The Amplifier Room

The high-power amplifiers used in radiated immunity tests produce a significant amount of heat and noise and can be uncomfortable for staff working in the control room. In large laboratories, amplifiers are therefore located in a separate shielded room. This room is placed as close as possible to the test chamber, because the shorter the cable between amplifier and antenna, the lower the power loss.

Air conditioning in the amplifier room should be planned with enough capacity to handle the heat the amplifiers generate. The amplifiers' power needs should also be taken into account in the room's electrical infrastructure. Control connections between the amplifier room and the control room are also made with fibre optics.

Product Monitoring Systems

Monitoring the product's behaviour during the test is critical, especially in immunity tests. The product's display, indicators and physical behaviour are monitored with cameras placed in the test chamber. These cameras must themselves be immune to noise, and their video signals carried to the control room over fibre optics.

The product's electrical outputs, communication lines and measured values are passed to the control room through fibre optic converters or special monitoring systems. The monitoring setup should be designed in line with the test plan so the product's performance criteria can be assessed. It should also be verified that the monitoring systems themselves are not affected during the test.

Size and Working Comfort

The size of the control room is set by the equipment inside, the number of staff and the laboratory's workload. Racks for measuring instruments, work desks, displays and an area for product preparation should be planned. In laboratories managing several tests at once, a separate control area for each test chamber or a shared control room serving several chambers can be designed.

Test engineers spend long hours in the control room, so working comfort should not be overlooked. Adequate lighting, quiet air conditioning, ergonomic workspaces and, if possible, an observation window looking directly into the test chamber improve efficiency. If an observation window is needed, shielded glass is used to preserve shielding.

Integration into the Laboratory Plan

The control room, test chamber, amplifier room and auxiliary areas together form a laboratory plan. This plan should be designed to ease the flow from accepting products into the laboratory to returning them after testing. Having the product preparation area close to the test chamber door makes moving heavy products easier.

In large laboratories, several test chambers can be managed from a single control centre. This arrangement increases staff efficiency and makes shared use of equipment easier. Laboratory planning should be done at the earliest stage of the project, together with test chamber design. For large-scale laboratory options see our SAC-10 page, and for other chamber options our semi-anechoic chamber page.

Frequently Asked Questions

How large should the control room be?

It depends on the equipment inside, the number of staff and the workload. Space should be planned for measurement racks, work desks and product preparation.

Does the control room also need high dB?

Usually a lower level than the test chamber is enough. The aim is that equipment in the control room does not affect measurements and that staff are protected.

How is the product monitored by camera?

Noise-immune cameras are placed in the test chamber and their video signals carried to the control room over fibre optics.

Can amplifiers be in the control room?

In small laboratories they can, but because of heat and noise, a separate amplifier room is preferred in large laboratories.

What is on the penetration panel?

Shielded coaxial feedthroughs for RF cables, fibre optic links for control and monitoring, filters for power and spare penetrations for future needs.

Does an observation window compromise shielding?

Not when shielded glass is used. Shielded glass preserves the view while blocking radio-frequency signals.

Let's Find the Right Solution for Your Project

Your free site survey and quote will be ready within 24 hours.

Get a Quote

Get a Quote

Step 1 / 2 · Your Project

What kind of room do you need?
Approximate size