Why Partial Discharge Testing Needs a Shielded Lab

Why partial discharge measurement in cable, transformer and insulator testing is so sensitive to outside noise, and the role of a shielded lab.

High-voltage cables, power transformers, switchgear and insulators are designed to operate reliably for many years. One of the most important causes of their early failure is small defects that develop over time inside the insulation material. Partial discharge measurement is the most reliable way to detect these defects before the equipment goes into the field.

But partial discharge signals are extremely small and easily affected by electrical noise in the surroundings. In this article we explain what partial discharge is, how small the measured signal is, how noise affects the measurement, how a shielded laboratory solves this problem and what to watch for in laboratory design.

What Is Partial Discharge?

Partial discharges are small electrical discharges that occur in tiny voids inside an insulating material, at interfaces between two materials or on the surface, without fully breaking down the insulation. Under high voltage, the electric field in these small regions exceeds what the material can withstand and a local discharge occurs. Although harmless on its own, each discharge erodes the insulation a little more.

Over time this erosion grows, the defect widens and eventually the insulation breaks down completely and the equipment fails. This process can take years, but the result is usually a sudden and costly failure. That is why measuring the partial discharge level is mandatory in post-production quality control and commissioning tests of high-voltage equipment. The measurement method is defined in IEC 60270.

How Small Is the Measured Signal?

Partial discharge is measured in picocoulombs (pC), as the apparent charge seen in the measurement circuit during the discharge. A picocoulomb is a trillionth of a coulomb. For many products, acceptance limits are between a few picocoulombs and a few tens of picocoulombs. Such a small signal requires very sensitive instruments and an extremely quiet electrical environment.

A signal like this is easily lost in noise from a nearby radio transmitter, a motor drive, a welding machine or even a fluorescent lamp. When the noise level approaches or exceeds the partial discharge level to be measured, the measurement cannot be made or the result is unreliable. For factories in industrial areas this is an especially serious problem.

Where Does the Noise Come From?

Noise affecting partial discharge measurements reaches the measurement circuit by two main routes. The first is airborne noise: radio and television transmitters, mobile base stations, two-way radios and other electrical equipment in the factory induce signals on the measurement circuit's cables and high-voltage connections. The large dimensions of high-voltage test setups make them good antennas.

The second is conducted noise. The mains line feeding the test setup can carry noise generated by other equipment in the factory. Problems in the earthing system can also let noise into the measurement circuit. Loose connections, sharp-edged metal parts or corona-producing fittings in the test setup itself can also create misleading signals.

  • Airborne: radio transmitters, base stations, two-way radios
  • From the mains: motors, drives and welding machines in the factory
  • From earthing: ground loops and faulty connections
  • From the setup: corona, loose connections, sharp edges

What a Shielded Laboratory Contributes

A shielded high-voltage laboratory isolates the test setup from radio-frequency noise in the outside environment. The laboratory's walls, ceiling and floor form a continuous conductive shield, so signals from outside transmitters cannot reach the test area. As a result, the background noise seen by the measurement circuit drops significantly and very low partial discharge levels can be measured reliably.

In addition to shielding, the laboratory's power supply is also filtered. The line feeding the test transformer passes through filters that suppress noise from the mains. Together, these two measures create a controlled, quiet electrical environment inside the laboratory. Shielded laboratories also prevent high-frequency noise generated during testing from affecting other parts of the factory.

Points to Watch in Design

The design of high-voltage laboratories involves requirements different from ordinary shielded rooms. The laboratory must be large enough to hold the largest equipment to be tested and the high-voltage setups. Sufficient clearances must be left between high-voltage connections and walls, ceiling and other earthed objects to prevent corona and flashover.

The earthing system is one of the most critical parts of the laboratory. A low-impedance, well-designed earth grid is needed for both safety and measurement quality. The connection between the laboratory's shield and the earthing system must be planned to prevent ground loops. Corona-free fittings and rounded electrodes should also be used in the test setup.

Shielding an Existing Test Hall

Many manufacturers consider shielding their existing high-voltage test hall. This is usually possible, either by building a shielded structure inside the hall or by lining the existing walls with conductive materials. However, the dimensions of the existing hall, the layout of high-voltage setups and the earthing system determine the scope and cost of the conversion.

Before conversion, a noise measurement in the existing hall is recommended. This measurement shows at which frequencies and by which path the noise arrives and helps determine the shielding level needed. In some cases, filtering the power line and improving the earthing system can give a noticeable improvement even without full shielding.

Who Needs It?

Shielded high-voltage laboratories are an important investment for cable manufacturers, transformer and switchgear manufacturers, insulator and insulating material manufacturers and the test centres of energy companies. These organisations must make reliable partial discharge measurements in their product quality control and customer acceptance tests.

Universities and research centres also need shielded laboratories for research on insulating materials and high-voltage technologies. For laboratory options, see our high-voltage laboratory page, and for our solutions for the energy sector, our energy sector page.

Frequently Asked Questions

Can an existing test hall be shielded?

In most cases yes. The suitable method is determined by evaluating the hall's dimensions, setup layout and earthing system.

What noise level can shielding achieve?

It depends on the ambient noise and the laboratory's design. In well-designed shielded laboratories, very low picocoulomb levels can be measured reliably.

Do you also install the earthing system?

We design and install the shielded structure's earth connection. The laboratory's general earth grid is planned in coordination with the facility's electrical design.

Which standard is partial discharge measured to?

The partial discharge measurement method in high-voltage testing is defined in IEC 60270; product standards set the acceptance limits.

What should the noise level be?

For a reliable measurement, background noise should be well below the accepted partial discharge limit, generally below half of it.

Is filtering the power line enough on its own?

In some cases it gives a noticeable improvement, but shielding is needed for airborne radio-frequency noise. Which dominates is determined by measurement.

Let's Find the Right Solution for Your Project

Your free site survey and quote will be ready within 24 hours.

Get a Quote

Get a Quote

Step 1 / 2 · Your Project

What kind of room do you need?
Approximate size